          Patna,(BiharTimes): The much publicized Ganga Driveway project once again found   no bidder after the project’s financial bid was opened on Friday after four   postponements.
 Left with no option the road construction department is   now likely to explore the alternative modes of executing the project.
 
 |  According to road construction minister Nand Kishore Yadav 12 firms had   responded to the expression of interest floated for the Ganga Driveway project.   Nine of those firms were shortlisted for the request for proposal (RFP)/   financial bidding stage. “But we found on Friday that none of the short-listed   firms submitted their bids,” he added. 
 The shortlisted firms included   Reliance Infrastructure, Welspun, Indus-C&C Consortium, Simplex Projects   Limited, Transstroy India Limited,and Nagarjuna Constructions.
 
 It must   be recalled that the date for opening the financial bid was postponed from   August 3 to August 14, yet no bidder turned up even that day.
 
 Once again   the deadline was extended to September 15, then to October 10 and again to   October 19. Yet the Public-Private Partnership project failed to find any   bidder.
 
 This is not the first time that Ganga Driveway project has met   the same fate. In past several decades a number of attempts, or at least   announcements, have been made in this regard, but it never yielded any result.   Several experts are of the view that it is not simply possible because of   environment.
    
	
	
       |